Production-readiness Soak Plan

Goal: validate the deployed v1.0 stack against real audio for 2 hours, with deliberately injected failures, before declaring the system event-ready.

Run this: AFTER Phase 1 + Phase 2 are deployed, BEFORE the deploy-frozen final week (2026-06-29 → 2026-07-01).

Total wall-clock: ~2.5 hours including setup and post-mortem.

Pre-flight (15 min before starting)

Soak timeline

T+0:00 — start session

T+0:05 — synthetic Cognito test

T+0:15 — network blip on bridge

T+0:30 — paused audio (silence banner test)

T+0:45 — Bedrock error injection (SIMULATION)

This is the trickiest one because we can't actually break Bedrock. Two options:

T+1:00 — engine deploy mid-session (Phase 1 drain validation)

This is the critical validation for Phase 1.

T+1:30 — alarm injection: silent-output

T+1:45 — long-tail soak

T+2:00 — measurement pass

Pull these metrics for the soak window:

Pass / fail

The soak passes if ALL of these are true:

If ANY of these fails, file it as a regression to fix before the event. Do not ship to production with known soak failures.

Post-soak review (with the team)

Within 24 hours of the soak: